July 2019 Update

July 2019 Capital Project Update

Byron-Bergen Central School District is committed to keeping the community updated as to the progress of the Capital Project. We are pleased to announce that the construction is currently on schedule. With multiple facets taking place simultaneously, we endeavor to provide a comprehensive list of ongoing and completed projects.

Ongoing:

  • =         Rooftop ventilation units for the Elementary School, Jr./Sr. High School, and Natatorium
  • =         Elementary School 200 wing corridor and classroom walls
  • =         Elementary School 100 wing office suite
  • =         Elementary School kitchen appliance and ventilation installation
  • =         Bus Garage bus wash installation
  • =         Jr./Sr. High School installation of new high-efficiency boilers
  • =         Jr./Sr. High School piping and pump installation
  • =         Jr./Sr. High School new theatre lighting
  • =         New tennis courts

Complete:

  • =         Elementary School kitchen tile, painting, ceiling, mechanical, electrical, plumbing
  • =         Elementary School cafeteria ceiling
  • =         Elementary School 200 wing asbestos abatement
  • =         New Natatorium roof
  • =         New Natatorium dehumidifiers
  • =         Old High School boilers removed
  • =         New practice soccer field

2019-2020 School Year Update

Specific information for the 2019-2020 school year as it impacts the class of 2026: 

The construction taking place at the elementary school creates a need for flexibility as improvements are made. The administrative team has collaborated with teachers, families, and students to try to make the transition as seamless as possible.


The class of 2026 will remain on an elementary school schedule and will continue to ride elementary transportation runs. Students will still have the option for early transportation to participate in intramurals, band and chorus.

The following will be the daily schedule for students:

  • 8:30 AM - Buses arrive in the Elementary School loop.  Students will be dismissed for breakfast.

  • 8:45 AM - Students will load shuttle buses at the elementary school.  There will be adult supervision to ensure that students who attend intramurals, chorus, band, or breakfast have boarded the bus.

  • 8:50 AM - Students will be transported to the Jr./Sr. High School to begin their day.

  • 11:36 AM - Students will eat lunch with 7th and 8th grade students.

  • 2:25 PM - Students will load shuttle buses back to the elementary school.

  • 2:30 PM - Students will participate in specials at the elementary school.

  • 3:20 PM - Students will dismiss from the elementary school as usual.

Parents or guardians dropping students off in the morning, rather than using district transportation, need to be at the Jr/Sr. High School by 9am. End of the day pick-ups will take place at the elementary school. Arrangements will be made to transport students for assemblies and other building wide activities during the school day at the elementary school.

For more information, the District is holding an orientation night for parents and students on Thursday, June 20 at 6pm in the Jr./Sr. High School auditorium.

Total Project: Planned Work

ELEMENTARY SCHOOL
  • Renovate and expand classrooms in 200 Wing
  • Alterations to toilet rooms to meet ADA compliance
  • Upgrade kitchen equipment
  • New light system on stage in Cafetorium
  • Replacement of aging windows
  • Safety improvements to driveway, bus loop and parent drop-off
  • Upgrade to mechanical equipment
STADIUM  
  • Installation of new bleachers at Soccer Stadium
HIGH SCHOOL
  • Installation of regulation size tennis courts
  • Improved stage lighting in Auditorium
  • Replacement of roof over gymnasium and auditorium
  • Upgrades to the fire alarm system
NATATORIUM & BUS GARAGE
  • Replacement of dehumidification system
  • Replacement of roof on bus garage and a section of the roof on the Natatorium
  • Replacement of bus wash system
The vote was held on Sept. 21, 2017, and passed by a vote of 338 YES - 112 NO.

Financial Impact

The total project cost is estimated to be $18,452,902 and the district will be using $2,000,000 in capital reserve to offset this cost.
This project will have a $0 impact on taxes.