Capital Improvement Project

Phase 1 Update

1/26/2018
Project Scope: Scheduled work for Phase 1
  • Jr./Sr. High School: Roofing replacement and Stadium Bleacher replacement
  • Elementary School: Classroom floor finish abatement/replacement; classroom ceiling replacement; classroom door frame restoration; classroom painting
  • Natatorium (pool): No work scheduled during Phase 1
  • Bus Garage: Roofing replacement 

Project Schedule

  • Phase 1 final submission paperwork sent to SED
  • Prescreen approval; issuance of project review number; declaration of third-party review following
  • District to approve A/E to pay BOCES ahead of review 

Project Budget: construction budget and incidental budget to be reviewed.

Total Project: Planned Work

ELEMENTARY SCHOOL
  • Renovate and expand classrooms in 200 Wing
  • Alterations to toilet rooms to meet ADA compliance
  • Upgrade kitchen equipment
  • New light system on stage in Cafetorium
  • Replacement of aging windows
  • Safety improvements to driveway, bus loop and parent drop-off
  • Upgrade to mechanical equipment
STADIUM  
  • Installation of new bleachers at Soccer Stadium
HIGH SCHOOL
  • Installation of regulation size tennis courts
  • Improved stage lighting in Auditorium
  • Replacement of roof over gymnasium and auditorium
  • Upgrades to the fire alarm system
NATATORIUM & BUS GARAGE
  • Replacement of dehumidification system
  • Replacement of roof on bus garage and a section of the roof on the Natatorium
  • Replacement of bus wash system
The vote was held on Sept. 21, 2017, and passed by a vote of 338 YES - 112 NO.

Financial Impact

The total project cost is estimated to be $18,452,902 and the district will be using $2,000,000 in capital reserve to offset this cost.
This project will have a $0 impact on taxes.